Order of cost estimate
The purpose of an order of cost estimate is to establish affordability of a proposed development for a client.
Methods for preparing order of cost estimates are set out in the New Rules of Measurement:
- NRM 1: Order of cost estimating and cost planning for capital building works
- NRM 3: Order of cost estimating and cost planning for building maintenance works.
NRM1 defines an order of cost estimate as; '...the determination of possible cost of a building(s) early in design stage in relation to the employer’s fundamental requirements. This takes place prior to preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process.'
A wide range of information may be required from the parties to the project to prepare an order of cost estimate:
From the employer:
- Location and availability of site.
- Statement of building use and size.
- Any refurbishment requirements.
- Initial project/design brief.
- Enabling works details.
- Draft programme.
- Site conditions.
- Budget/cash flow constraints.
- Construction procurement options.
- Life span of the proposed building.
From the architect:
- Design study sketches or drawings.
- Schedules of areas.
- Legislative constraints.
- Initial risk register.
Information can also be provided by the services engineer, structural engineer, and other consultants if these have been appointed.
The key constituents of an order of cost estimate are typically:
- Facilitating works.
- Building works.
- Contractor’s preliminaries.
- Contractor’s overheads and profit.
- Construction cost.
- Fees.
- Other development/project costs.
- Risk allowances.
- Inflation.
Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines an order of cost estimate as: ‘An estimate based on benchmark data for a similar type of project based on a defined brief.’
[edit] Related articles on Designing Buildings
Featured articles and news
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.